Knockdown rebuild

Knockdown rebuild in Perth, matched to the right builder

If your block is in the perfect spot but your house has reached the end of its life, a knockdown rebuild can offer a fresh, modern home without having to sacrifice the suburb you love.

A period brick home shown alongside a rendered concept of a modern rebuild
3500+
homes delivered
$960M+
contract value managed & delivered
Tier 1
industry pedigree & builder relationships
Where to start

Do I renovate, or just start fresh?

House & Land Co are Perth’s knockdown rebuild specialists and help to streamline every step, from home demolition in Perth to handing over your new keys.

If you already own land (or are inheriting family land), many Perth homes built decades ago no longer meet modern standards for layout, energy efficiency or liveability. Rather than renovating around old problems, knocking down and rebuilding from scratch gives you a clean start, a contemporary design and a significant increase to asset value, all without leaving your postcode.

A newly built single-storey Perth home at dusk with a timber and stone entry
Why people do it

The demolish & build advantage

Stay in your ideal location

A knock down and rebuild lets you remain close to schools, transport, family and lifestyle essentials. You keep everything you love about your suburb while completely upgrading your home.

Modern design on your terms

Choose a layout that suits your current lifestyle, not one from decades ago. Our builder network offers flexible homes with smart layouts, natural light, modern features and future-proof design options.

Avoid hidden costs and patchwork headaches

Renovations can uncover structural issues, electrical problems or water damage that balloon your budget. A tear down and rebuild replaces constantly changing costs with a predictable, fixed-price solution.

Increase your land value with a modern home

Replacing an ageing property with a new build immediately improves street appeal and boosts long-term value. A modern home makes far better use of a Perth block and strengthens your future resale potential.

Fast, fixed-price builds through our builder network

We compare Perth’s leading rebuild specialists for you, securing competitive pricing, clear timelines and strong warranties, so the process is smooth and managed by professionals who do this every day.

Suits investors, retirees, upgraders & subdividers

Whether you’re an investor wanting a low-maintenance rental, a family needing more space, or a homeowner exploring subdivision, these packages can be tailored to suit any goal.

Our proven knockdown rebuild process

01

Council approval, demolition & site preparation

We handle the tricky parts: lodging the correct paperwork, obtaining demolition quotes, organising any necessary site works, and giving you a clear estimate of what it will cost to knock down your house.

02

Design, compare & customise

Once the site is set, we explore design options and builders that suit your budget and vision. You pick a floorplan, we show you comparable builds and specs, then help personalise what matters most: layouts, storage, finishes and fittings.

03

Sign, build & get the keys

After approvals and contracts, construction begins at a fixed price you can trust. We keep you updated, handle any issues that crop up and make sure the build stays on track, right through to handover.

FREE GUIDE

The step-by-step guide to a knockdown rebuild

Nine pages, in plain English. What a knockdown rebuild actually involves, what to check on your own block before you spend anything, and the costs that catch people out.

We will email you the guide and may follow up once about your block. No spam, and you can ask us to stop at any time.

Cover of the House and Land Co knock down rebuild guide
Model the numbers

What would the repayments look like?

You already own the block, so there is no land to buy. This models the repayments on the build itself.

Step 1 — your loan

Repayment Calculator

1 yr15 yrs30 yrs
Repayment type
Frequency

These figures use the same APRA-aligned 9% serviceability assessment your lender will apply. Indicative only — speak with a House & Land Co specialist for personalised advice.

Your repayment estimate

Fill in the form and click Calculate to see what your loan would cost each week, fortnight or month.

Before you rely on a number

An estimate based on what you enter, not a loan approval or financial advice. Your lender will assess your situation on its own criteria.

The full cost

What a knockdown rebuild costs, beyond the build price

A knockdown rebuild is two projects sharing a block. One is a demolition, run by your council and three utilities. The other is a build. Budgets go wrong when the first is treated as a line item in the second.

The fees that are fixed before anyone quotes

Before a demolition contractor prices anything, the demolition permit, the Building Services Levy and the water, power and gas disconnections come to about $3,340 on a house with gas connected, plus a refundable verge bond set by your council. The building permit for the new home is on top of that: on a $450,000 certified build, the permit fee and levy add roughly another $1,470. We list every fee, who charges it and where it is published in what it costs to demolish a house in Perth.

Rent and loan interest

You cannot live in the house while it is being built. Plan on twelve to eighteen months of rent somewhere else while you pay interest on the drawn part of your construction loan. Neither is on a builder’s quote, because neither is the builder’s to charge. For most households it is the second-largest number in the project, so put it at the top of the budget, not the bottom.

What the build price leaves out

An advertised home design price is the house, not the project. Site works priced from your soil classification, retaining where the block falls, stormwater and the driveway crossover all sit outside it. Ask for quotes with separate lines for demolition, asbestos survey, licensed removal, disconnections, tipping, site works and the crossover, and ask which are fixed prices and which are provisional sums. Two quotes that include different things are not two quotes.

Why the totals you read online disagree

Two of the most-read Perth pages on this both say twelve to eighteen months. One means demolition through to handover. The other means slab down, leaving out planning and demolition. Before you compare any figure, find out where it starts and stops counting.

Approvals and timing

How long it takes, and the approvals that set the pace

Plan for around eighteen months from first quote to handover. The stages that slip are almost never the construction. They are the approvals and disconnections at the front, where most people start too late.

The demolition permit

Section 10 of the Building Act 2011 makes it an offence to demolish without a permit. You apply on form BA5 to your local government. Regulation 20 of the Building Regulations 2012 gives the council 10 business days to decide, or longer only if you agree in writing. If it misses that deadline, the application is taken to be refused and the fee is refundable as a debt owed to you.

The building permit

The permit for the new home is a separate application with its own clock:

Building permit decision periods and fees in Western Australia
ApplicationDecision periodFee
Certified, form BA110 business days0.19% of the value of the work, minimum $121.00
Uncertified, form BA2 (Class 1a and Class 10 only)25 business days0.32% of the value of the work, minimum $121.00

A certified application arrives with a certificate of design compliance from an independent building surveyor, which is why it is decided faster. Most volume builders lodge certified as a matter of course. Source: Building and Energy.

Planning approval, when it also applies

A single house that meets the deemed-to-comply provisions of the Residential Design Codes can often go ahead on a building permit alone. Planning approval is more likely if your block is in a heritage or character area, if the design varies the setbacks or open space requirements, or if you are subdividing. This is the step that adds months rather than weeks. The R-Codes are no longer State Planning Policy 7.3: since April 2024 they are a Planning Code under the Planning and Development Act 2005, currently Residential Design Codes Volume 1, Version 3.

The realistic timeline

A realistic knockdown rebuild timeline in Perth
StageHow long
Design, quotes, finance and contract2 to 4 months
Gas disconnectionUp to 20 business days after processing, so lodge it first
Electricity abolishmentAllow 5 business days, plus the Disconnected for Demolition Notice
Water disconnectionNo published lead time, so start early
Demolition permit10 business days statutory, plus the council's queue
Asbestos removal and demolitionThe demolition takes days; the process around it takes weeks
Building permit10 business days certified, 25 uncertified
ConstructionSet by your building contract. Get the construction period in writing before you sign
Your block

What your block does to the price

Two blocks in the same street can price thousands apart for the same house. The difference is under the ground and around the edges.

Site classification

Before the slab is designed, an engineer classifies the soil under Australian Standard AS 2870. The class drives the footing design, and the footing design drives the site works cost.

AS 2870 site classes
ClassWhat it means
AMost sand and rock sites, little or no ground movement from moisture changes
SSlightly reactive clay, slight ground movement
MModerately reactive clay or silt, moderate ground movement
H1Highly reactive clay, high ground movement
H2Highly reactive clay, very high ground movement
EExtremely reactive, extreme ground movement
PProblem sites: soft or loose soils, landslip, mine subsidence, collapsing soils, erosion, abnormal moisture, or sites that cannot otherwise be classified

Filled sites are classified A to P depending on what is under them. Your neighbour’s classification tells you very little, particularly in older suburbs where fill went in unevenly. Insist the soil test is done on your land, after demolition where possible, and that the site works figure is priced from it. Definitions from AS 2870 as reproduced in the National Construction Code.

Slope, access and what is under the slab

Fall across the block drives cut, fill and retaining. A narrow verge, a tight driveway or a power line across the frontage decides whether the crew can use standard machinery. What sits under the old slab, such as a septic system, a filled-in pool or rubble fill, is only found once the house is gone, which is why site works is so often a provisional sum.

Asbestos

If your home was built before 1990, assume there is asbestos until a survey says otherwise. On a knockdown rebuild its removal is licensed work, and it is the owner’s cost. Get the survey done before you sign anything with a demolition allowance in it. We set out the licence classes and what the law requires in our demolition cost guide.

Your contract

Your contract protections, and their limits

The Home Building Contracts Act 1991 covers fixed-price residential building contracts between $7,500 and $500,000. Inside that band, a builder can take a deposit of no more than 6.5% of the contract price, and must hold home indemnity insurance and give you the certificate before starting work or asking for any payment on work valued over $20,000.

Two limits matter on a knockdown rebuild. Above $500,000 the Act does not apply and there is no deposit cap, and plenty of Perth rebuilds now go over that figure. And demolition sits outside the Act altogether, so a stand-alone demolition contract has no deposit cap and no home indemnity insurance. Ask who holds the demolition contract and on what terms before you sign either one.

The WA Government is reviewing these thresholds in 2026, so check the current figures with Building and Energy before you sign.

Weighing it up

Is a knockdown rebuild right for you?

A rebuild is ideal if your current home needs major upgrades, your block itself is especially valuable, or renovation costs are close to what a brand-new home would demand.

Knock down and rebuild compared with renovating an existing Perth home
Knock down & rebuildRenovate
Cost certaintyA predictable, fixed-price solution, designed from the ground upCosts can change as problems are uncovered mid-project
Hidden problemsYou start from a clear site, so there is nothing to uncoverStructural issues, electrical problems or water damage can appear
LayoutA design that suits how you live nowWorking around a layout drawn decades ago
Modern standardsBuilt to current standards for energy efficiency and liveabilityOlder homes may not meet modern standards for layout or efficiency
Land valueImmediately improves street appeal and long-term resale potentialImprovement is limited by the existing structure

This is our case for rebuilding, and it will not be right for every block. We have written a longer, balanced comparison at knock down rebuild vs renovation. Worth reading before you decide.

Don’t risk the wrong builder

Choosing a knockdown builder in Perth matters: difficult sites, older suburbs and demolition stages all need specialised experience. We help you compare the right builders so you avoid costly delays or oversights.

Questions

Knockdown rebuild questions we get most

What does a knockdown rebuild cost in Perth?

There is no useful average, because the block is the variable. Budget the stack rather than the build: demolition and asbestos, about $3,340 in fixed permit and disconnection fees, the building permit fee and levy, site works, the house itself, and twelve to eighteen months of rent and loan interest. Price each line against your own block.

Is a knockdown rebuild worth it?

It is worth it when the location carries the value and the house does not. The honest test: would you pay today’s land value for the block with nothing on it? If yes, a rebuild usually stacks up. If the house is sound and the problem is the layout, read knock down rebuild vs renovation first.

Is $400,000 enough to build a house in Perth?

For a knockdown rebuild it is the wrong question, because a build price is not a project price. It leaves out demolition, asbestos, the fees and disconnections, the building permit, site works priced from your soil test, and your rent and loan interest while you wait. Ask a builder what their price includes and what it assumes about your block, then add the rest around it. We will do that with you at no cost.

Do I pay stamp duty on a knockdown rebuild?

No. You already own the land, so there is no transfer and no transfer duty (stamp duty) on the property. That is one of the real financial advantages over buying an established home somewhere else. Confirm your own position with your settlement agent.

How long does a knockdown rebuild take?

Plan on about eighteen months from first quote to handover. The approvals have statutory clocks of 10 to 25 business days, but the gas, power and water disconnections ahead of them set the real pace. Lodge the gas disconnection first.

Get in touch about your rebuild

Bring us your block. We will look at what it can take, compare the builders who actually do this work, and give you a straight answer, at no cost to you.